Lafey Construction Loses Court Appeal After KeNHA Cancels KSh3 Billion Tender Over Forgery Claims
Lafey Construction had secured the KSh3 billion road tender, furnished performance guarantees and prepared to execute the contract. But after KeNHA cancelled the award over alleged forged documents, the Court of Appeal ruled that the company had approached the wrong forum. Its legal battle now faces another hurdle, with the merits of the cancellation still unresolved.
A KSh3 billion road contract has triggered a significant legal battle involving KeNHA and Lafey Construction Company Limited.
The Court of Appeal has dismissed the contractor’s challenge against cancellation of its lucrative road construction award.
However, the judges stopped short of determining whether KeNHA lawfully terminated the procurement.
They ruled that Lafey should first use the statutory review process instead.
The dispute concerns Tender No. KeNHA/2915/2025 for upgrading the Masara–Muhuru Bay (B1) Road.
Lafey emerged as the lowest bidder after KeNHA evaluated competing submissions.
The authority recommended the company for the award, subject to due diligence.
On January 12, 2026, KeNHA notified bidders of its intention to award Lafey.
The statutory standstill period subsequently expired on January 27.
KeNHA issued the company an award letter on January 28, 2026. The contract was valued at KSh3,013,648,316.91, with 60 months allocated.
Lafey maintained that it fulfilled every condition attached to the award.
These included submitting acceptance, performance guarantees and contractors’ all-risk insurance policies.
The company further claimed that both parties signed contract documents at KeNHA’s offices.
It consequently believed the project would proceed as awarded.
That expectation collapsed following allegations concerning its supporting procurement documents.
Forgery Allegations
On March 12, 2026, KeNHA received a complaint from A. Ngatia & Associates Advocates.
The complaint alleged that Lafey had forged documents supporting its construction experience.
Specifically, it questioned subcontracting documents involving China Railway No. 5 Engineering Group.
KeNHA notified Lafey Construction about the allegations before terminating the award. The authority subsequently invoked Section 63(1)(i) of procurement law.
On May 7, 2026, KeNHA formally communicated its decision to terminate the tender.
Five days later, it advertised another tender covering the same project.
The replacement procurement carried reference number KeNHA/2953/2026.
Lafey considered the development an unlawful attempt to discard its award.
The company approached the High Court seeking permission to commence judicial review proceedings.
It wanted the termination and replacement advertisement quashed.
It also sought mandamus compelling KeNHA to proceed with the original contract.
Additionally, it wanted orders suspending further procurement proceedings.
Lafey explained that its director, Mohamed Maalim Kulmia, had fallen seriously ill.
His condition allegedly prevented him from managing company affairs and instructing lawyers promptly.
However, Justice William Musyoka dismissed the application on September 18, 2026.
He held that Lafey had failed to exhaust the statutory dispute resolution mechanism.
The judge directed the company towards the Public Procurement Administrative Review Board.
Lafey subsequently appealed, challenging that interpretation of procurement law.
The Legal Test
The appeal turned on interpreting Sections 63 and 167 of the Public Procurement and Asset Disposal Act.
Section 63 allows accounting officers to terminate procurement proceedings under specified circumstances.
These include subsequent evidence of fraudulent or corrupt practices by tenderers.
However, the provision expressly refers to termination before notification of award. That restriction formed the foundation of Lafey’s principal legal argument.
The company also relied on Section 167(4)(b), which excludes certain terminations.
It argued that the provision removed the Board’s jurisdiction entirely.
The appellate judges rejected that interpretation, drawing an important legal distinction.
They held that the exclusion only protects terminations lawfully undertaken under Section 63.
Where legality is disputed, the Board retains jurisdiction to examine compliance.
It can determine whether termination followed proper procedures and credible evidence.
The judges stated that bidders could challenge termination before the PPARB.
The Board would test whether the decision was “lawful, procedural and grounded in real evidence”.
However, the judges clarified that the Board cannot review lawful terminations.
Where accounting officers strictly comply with Section 63, jurisdiction ends.
In the judges’ words, the Board must then “down its tools”. This distinction effectively dismantled Lafey’s argument against administrative review.
The court consequently held that approaching the High Court was premature.
The company should have challenged KeNHA’s decision before the Board.
Questions Remain
The judges also rejected Lafey Construction’s complaint about procedural fairness at the High Court.
The company argued that Justice Musyoka raised jurisdiction without inviting submissions.
It maintained that this violated its constitutional right to a fair hearing. The appellate judges disagreed, emphasising that jurisdiction determines judicial authority.
They held that courts can examine jurisdiction at any stage. Even a judge preparing a ruling may independently identify jurisdictional problems.
The court further acknowledged Lafey’s complaints concerning alleged violations of fair hearing rights. However, it declined to determine those substantive questions.
The judges instead relied on the exhaustion doctrine and its established exceptions.
They cited the Supreme Court’s decision in Abidha Nicholus v Attorney General.
That decision recognises exceptions where alternative remedies prove inadequate or ineffective.
The appellate court found no sufficient reason to bypass the Board.
It therefore concluded that Lafey had failed to exhaust available remedies. The three judges dismissed the appeal without making costs orders.
The November 6, 2026 judgement leaves important questions unresolved. It does not establish whether Lafey actually forged procurement documents.
READ ALSO: Court Orders KSh34 Million Payment After KSh128 Million James Gichuru-Rironi Award
Neither does it finally determine whether KeNHA lawfully invoked Section 63. The court settled the proper forum, not the underlying controversy.
For Lafey, the immediate setback is substantial, given the contract’s value. For KeNHA, however, the judgement is not an outright vindication.
The legality of the cancellation remains distinct from the jurisdictional ruling. That distinction leaves the substantive procurement dispute far from settled.